Process Performance Qualification (PPQ) Services for Biologics: Prerequisites, Protocol and Batches

Process performance qualification is the Stage 2 campaign in which a biologics process is run at commercial scale, under a pre-approved protocol with enhanced sampling, to prove it reproducibly delivers conforming product. It requires a qualified facility, validated analytical methods and completed process characterization, and the number of batches must be justified rather than assumed.

Process Performance Qualification (PPQ) Services for Biologics: Prerequisites, Protocol and Batches

Process Development & Validation
Process Performance Qualification (PPQ) Services for Biologics: Prerequisites, Protocol and Batches

Process performance qualification is the Stage 2 campaign in which a biologics process is run at commercial scale, under a pre-approved protocol with enhanced sampling, to prove it reproducibly delivers conforming product. It requires a qualified facility, validated analytical methods and completed process characterization, and the number of batches must be justified rather than assumed.

Insights · 9 min read · Updated 2026

Key definition. Process performance qualification (PPQ) is the element of process validation that combines the qualified facility, utilities, equipment and trained personnel with the commercial manufacturing procedure to demonstrate, through a defined number of batches tested against pre-set acceptance criteria, that the process performs as designed.

PPQ in the FDA process validation lifecycle (Stage 2)

Process performance qualification is the second half of Stage 2 in the FDA's 2011 guidance Process Validation: General Principles and Practices, the point at which development knowledge is tested against commercial reality. Stage 1, Process Design, establishes the process and its control strategy. Stage 2, Process Qualification, covers facility, utility and equipment qualification, then PPQ itself. Stage 3, Continued Process Verification, maintains the validated state in routine manufacturing.

The guidance replaced the older idea of "three validation batches" with a lifecycle in which evidence accumulates before and after the PPQ campaign. It also expects commercial distribution to wait until PPQ is complete, with concurrent release allowed only in defined, justified circumstances.

The EU framework reaches the same place by a different route. EU GMP Annex 15, Qualification and Validation (in operation since 1 October 2015), describes traditional, continuous and hybrid approaches to process validation, requires acceptance criteria to be set before the batches are run, and expects the batch number to be justified by quality risk management.

Prerequisites: qualified facility and equipment, validated methods, completed characterization

A process performance qualification campaign can begin only when four prerequisites are closed, and campaigns fail most often because one was treated as parallel work rather than a gate. Each should have an approved report before the first PPQ batch starts.

  • Facility, utility and equipment qualification. Installation, operational and performance qualification for cleanrooms, HVAC, water for injection, clean steam, bioreactors, chromatography skids, filtration and the control system.
  • Validated analytical methods. Every release, in-process and characterization method in the protocol validated for specificity, range, accuracy, precision and, where relevant, LOD and LOQ, and transferred to the laboratory that will test PPQ samples.
  • Completed process characterization. Critical process parameters, proven acceptable ranges and the control strategy approved, because they define what PPQ monitors and what counts as success.
  • Supporting validation. Cleaning validation, hold-time studies, mixing studies, filter validation, resin and membrane lifetime protocols and shipping validation completed or scheduled alongside the campaign.

An engineering batch at commercial scale is not formally required but is standard practice; it finds procedural errors at a fraction of the cost of a failed PPQ batch.

EirGenix in practice

EirGenix's mammalian cGMP facility holds Taiwan FDA cGMP certification (2005), Taiwan FDA PIC/S GMP certification (2014, current), Japan PMDA approval (2020) and US FDA approval (2023). Its critical equipment list includes 100–500 L stainless-steel trains, 50–2,000 L single-use trains, 0.1–14 m² UF units, 5–60 cm low-pressure chromatography columns and a central control system.

Protocol elements and acceptance criteria

The protocol is the scientific definition of the process performance qualification, and every element the FDA guidance lists should be present and approved by the quality unit before execution.

Protocol elementWhat it must specifyTypical acceptance criterion
Manufacturing conditionsOperating parameters, processing limits, raw material and component inputs for every unit operationAll critical process parameters within normal operating range in every batch
Data to be collectedParameters and attributes recorded, at what frequency, and how evaluatedComplete data set; no unexplained gaps
Tests and acceptance criteriaIn-process, release and additional characterization tests with pre-set limitsAll release results meet specification; in-process results meet protocol limits
Sampling planSampling points, number and frequency, more extensive than routineAll planned samples taken and tested
Statistical criteriaHow intra- and inter-batch variability is assessed; methods and confidence levelsPre-defined, for example process capability or tolerance intervals meeting a stated target
Facility, equipment and personnel statusQualification reports, training records, material qualification and analytical method validation statusAll referenced documents approved before execution
Deviation handlingHow deviations, OOS results and amendments are managedProcedure defined; quality unit approval required for amendments
Review and approvalManufacturing, QC, QA and, where applicable, sponsor signaturesApproved before the first batch starts

Two choices cause most later disputes: whether in-process acceptance criteria sit at the release specification or at tighter limits derived from characterization, and how a batch is judged when one enhanced-sampling result misses its protocol limit but release results pass. Both belong in the protocol, not in the report.

How many PPQ batches: justify, do not default to three

Neither the FDA guidance nor Annex 15 fixes the number of process performance qualification batches, and both require it to be justified. Annex 15 states that a minimum of three consecutive batches under routine conditions could constitute a validation of the process, while requiring each manufacturer to justify its own number. The FDA guidance ties the number to the manufacturer's confidence in the process, based on development knowledge and prior experience.

The justification should rest on identifiable factors: variability seen in clinical and engineering batches, process complexity and novelty, platform precedent, the statistical approach to inter-batch consistency, and the degree of enhanced sampling. Three batches remain common for antibodies on well-understood platforms. Novel formats, high-variability steps, or a need for narrow capability estimates often justify four or five. A protocol can also set a minimum number with pre-set triggers for additional batches if variability exceeds expectations.

EirGenix in practice

EirGenix's Zhubei site, operational since 2019, runs 2,000 L single-use bioreactor trains with an annual antibody production capacity of up to 1,000 kg, and the company describes commercial-scale production of successfully marketed products.

Enhanced sampling beyond routine release

Enhanced sampling distinguishes a process performance qualification batch from a routine batch, and the FDA guidance is explicit that PPQ will in most cases involve more sampling, additional testing and greater scrutiny than routine production. The purpose is to characterize intra- and inter-batch variability well enough to justify the Stage 3 monitoring plan.

For a mammalian drug substance process, enhanced sampling typically adds:

  • Daily bioreactor samples for cell density, viability and metabolites, plus product-quality attributes such as glycan profile and charge variants at defined days.
  • Impurity clearance at every purification step: host cell protein, host cell DNA, residual Protein A and aggregates on each column pool, not only on final drug substance.
  • Bioburden and endotoxin at every intermediate hold, with at least one batch run to the maximum validated hold time.
  • Column yield, pool volume, transition analysis and pressure profile for each cycle.
  • Bulk homogeneity sampling from top, middle and bottom of the final container, plus extra containers on stability.

Each added sample needs a validated method and either an acceptance criterion or a "report result" designation decided in advance; data without a pre-set criterion invite questions at inspection.

The PPQ report and its place in BLA Module 3

The process performance qualification report converts batch data into a validated process, and it is what the reviewer and the pre-license inspector read. The FDA guidance expects it to cross-reference every protocol element, summarize and analyze the data, evaluate unexpected observations, describe corrective actions, and state a clear conclusion with quality unit approval.

In the Common Technical Document, the drug substance PPQ summary is filed in Module 3 section 3.2.S.2.5, Process Validation and/or Evaluation, with the control strategy in 3.2.S.2.4 and development history in 3.2.S.2.6. Viral clearance validation is filed in 3.2.A.2, Adventitious Agents Safety Evaluation; drug product PPQ follows 3.2.P.3.5. The dossier carries a summary with batch results tabulated against acceptance criteria; the full report stays at the site for inspection.

Timing is tight. PPQ batches must be complete, with initial stability data, before a BLA is submitted, and the pre-license inspection will walk the PPQ batch records.

What a CDMO's PPQ service covers

PPQ services from a CDMO should cover the process performance qualification campaign from protocol drafting to report approval, and a sponsor comparing PPQ services should check for each item below rather than for the phrase "process validation" alone.

  • Facility, utility and equipment qualification reports available for sponsor review and inspection.
  • Validated and transferred analytical methods for every protocol test, with method validation reports.
  • Protocol authorship with sponsor approval, including the statistical plan and the batch-number justification.
  • Enhanced sampling execution and sample management, including stability placement.
  • Deviation and out-of-specification investigation under the site quality system, with sponsor notification terms in the quality agreement.
  • Supporting validation: cleaning, hold times, resin and membrane lifetime, filter validation, shipping.
  • PPQ report authorship, Module 3 section drafts and pre-license inspection support.
  • A defined transition into Stage 3, with the continued process verification plan agreed before the campaign ends.

The quality agreement should state who approves the protocol, who owns deviations and how a failed batch is handled commercially, because once the campaign is running these decisions are made under time pressure.

Frequently asked questions

Can PPQ batches be sold commercially?

Yes, provided the batches meet all release specifications, the process performance qualification succeeds, and the product is approved. The FDA guidance expects PPQ to be complete before commercial distribution begins, and allows concurrent release only in justified cases such as limited demand or short shelf life. Batches made before approval are typically held as launch stock.

What happens if a PPQ batch fails?

The failure is investigated under the site deviation system, and the batch cannot simply be dropped from the data set. If the cause is assignable and unrelated to the process, such as an equipment fault, the protocol may allow a replacement batch with documented justification. If the cause is process-related, the process is corrected and the process performance qualification is repeated, usually after a review of the characterization data.

Does a site change require a new PPQ?

In almost all cases, yes. A new site means new equipment, utilities and personnel, so process performance qualification is repeated there, supported by an ICH Q5E comparability exercise against material from the original site. For an approved biologic, a site change is normally a prior approval supplement, and the agency may inspect the new site first.

About EirGenix

EirGenix, Inc. (stock code 6589) is a Taiwan-based biologics CDMO and biosimilar developer founded in 2012, with cGMP facilities in Xizhi (New Taipei City) and Zhubei (Hsinchu County) and a European subsidiary in Munich. Its mammalian manufacturing site holds Taiwan FDA PIC/S GMP certification (2014), Japan PMDA approval (2020) and US FDA approval (2023), and the company's trastuzumab biosimilar EIRGASUN®/HERWENDA® received EU marketing authorization in November 2023 with Sandoz as marketing authorization holder. EirGenix provides cell line development, process development, analytical and quality control services, cGMP manufacturing in mammalian and microbial systems, and ADC and bioconjugate development and manufacturing.

Plan your PPQ campaign

Discuss commercial-scale manufacturing for your validation campaign with the EirGenix mammalian manufacturing team.